The policy of municipal assets Lorca covers over 102 million in damages (29/08/2011)

The City has filed a complaint with the Consortium and will resort to the courts if necessary to obtain compensation for the 40 million it deserves.

From the Consistory belie the claims of Manuel Soler.

From the city of Lorca is reported that the policy of municipal assets to cover Lorca 102,117,947.62 in damages, which correspond to continent 88,977,816.12 euros (compared with explicit valuation of assets and themselves), EUR 8,011,487.43 EUR 5,128,644.07 content and works of art, it is not even contemplating the implementation of the proportional rule.

These figures would be more than covered the approximately 40 million in damages suffered by local properties, as the contract marks more than double the cost of repairs and replacements to be performed.

However, the Insurance Compensation Consortium has said it is only willing to pay 6.975 million euros, much less than the cost of restitution of damages, which the consortium is also making many records of individuals and businesses on what the City has filed a complaint with the Consortium and have recourse to the courts if necessary to obtain compensation for all the capital that it is entitled under the policy written with a capital of over 102 million and premiums paid.

The City Council reported that the Insurance Compensation Consortium "prefer not to meet its legal obligation to Lorca reflected in the Statement of Administrative Terms and technical specifications for this insurance."

In this sense, the Consistory has denied the claims of socialist Manuel Soler, apparently unaware of the conditions of the tender, as it has applied today.

The Insurance Compensation Consortium gives as valid a clause ceiling for compensation, which really was not in force because the policy takes over and again that any contradiction with the tender documents will not be set, in addition, the legislation itself The legal doctrine and jurisprudence unanimously agree that at the tender awards by the specification is binding between the parties and this was not contemplated at no time limit for extraordinary risks or to the sum insured in respect of and contents.

Therefore, the City Council requires the consortium to take its rightful spending because sooner or later have to pay it, and meanwhile is producing injury to the Lorca who can not make use of its facilities, among which are local social venues such as social services councils, sports facilities such as Europe or the Library Complex Pilar Barnes, among others.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información