Lorca City Council allocated € 392,733 grant from the Ministry of Development for the districts to remodel the street Alonso Vargas of El Calvario (20/01/2016)

The Mayor, Francisco Jodar, and the Director General of Urban Planning at the Ministry of Public Works, Nuria Fuentes, met last night with neighbors to agree on the final performance, which will begin in the coming days.

The Mayor of Lorca, Francisco Jodar, and the Director General of Planning and Housing of the Ministry of Public Works and Infrastructure of the Autonomous Community, Nuria Fuentes, along with Councilman Hall Works of Lorca, Eulalia Ibarra, met last night with the neighbors of El Calvario to present the proposal to remodel the street Alonso Vargas and listen to their proposals.

Jodar told the neighbors that "the grant of 10 million euros that the regional government granted the Consistory Lorca to reshape the districts of Lorca, Lorca fruit of the commitment of President Pedro Antonio Sanchez and the Minister Francisco Barnabas, will be allocate € 392,733.64 to the overall improvement of this road, which will include the demolition of 2562.4 m2 of flooring, replacement of all services that require improvement and a new surface treatment ".

Thus, the water supply network will be renewed, with the installation of 430.35 meters of new pipe diameter 100 for the grid.

Also, a hydrant is placed at crossing the street Alonso Vargas, in order to facilitate rapid and effective action in case of fire.

In addition, the renewal of 396.83 linear meters of sewer wastewater collection is expected by PVC pipe 315 and the construction of a new PVC pipe 400 134.57 meters.

Similarly 436 meters of underground pipeline will be made for the installation of street lighting and wiring installation type LED lamps 32, 10 with model lantern lights 48W 24 next-generation LEDs to 130 lumens on casting wall bracket 22 and 24W luminaires bluff 12LEDS model.

An underground network of 871 linear meters for underground sewer lines and other low voltage of 420.5 linear meters so that telecommunications companies can perform the burial of wiring will also be created.

The completion of the project includes the top of the street is fully treated at the same level with cobblestone, differentiated by the color the pedestrian area of ​​the shot, while from the Franco Street until mid Street sidewalk cobblestone will be created with a small step separation zone vehicles, which will in asphalt.

The work will begin in the coming days and will last for about 8 months since its inception.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información