Crossing neighbors Campuzano, Marsilla Street and Plaza del Ibreño of Lorca decide how they want improvements to be made with regional funds (04/02/2016)

Lorca City Council representatives and the Ministry of Public Works and Infrastructure of the Autonomous Region met last night and Tuesday with residents in these areas in order to take into account their views ahead of the investment of 397,240.36 euros to be launched in the coming days to renew both services and the surface of these public spaces.

The residents of the neighborhood Campuzano crossing the gully of Tejares, and Marsilla Street and Plaza del Ibreño in the historic town of Lorca, have decided this week how they want to improve these roads, which will be built to grant the Ministry of Public Works and Infrastructure of the Autonomous Community granted to the City of Lorca for the remodeling of the district of San Cristobal and the districts of Lorca and its surroundings.

With this objective, the General Director of Planning, Architecture and Housing, Nuria Fuentes, and the mayor of Lorca, Francisco Jodar, met last night with neighbors Marsilla Street and Plaza del Ibreño and last Tuesday night councilman Works, Eulalia Ibarra, held a meeting with residents of the gully of Tejares.

Specifically, these actions represent an investment of 397,240.36 euros 241,922.46 euros distributed to the most central project and 155,317.90 euros for the neighborhood;

the first being actuated in a space of 1,319.54 m2 and the second in 860.46 m2, which will involve the complete renovation of underground utilities and pavement, which will have a similar treatment being done throughout the environment, with cobblestone rolling black to red for vehicles and pedestrians, with a white line of demarcation.

Crossing a hydrant in Campuzano

Thus, one of the major developments in the cruise Campuzano will be the installation of a hydrant facilitating action of firefighters in case a hypothetical fire in the area.

However, 8 LED lamp type lighting will also be installed, whose energy consumption is less than existing despite providing the same function, while being channeled into the 169.5 meters underground wiring lighting, and placed 528 meters of conduits for the burial of low-voltage lines, and 219 other meters for the burial of telephone networks.

Furthermore, in this street 160.84 meters of cast iron pipe and 42.5 meters polyethylene pipe for water supply network will be installed;

and 183.5 meters of PVC pipes for sewage, which will prevent clogging problems in the future.

Maintain the essence of the Plaza del Ibreño but with improvements

During the meeting with the residents of the Plaza del Ibreño Marsilla street and explained that the performance respect the essence of this area, retaining elements as the source and its semicircular design.

However, the area will be improved with the creation of a network of 100 linear meters of a network of rainwater collection, independent of 165.2 meters of new pipes to be installed in the sewage system, in order to reduce the consequences of the rains, for which it has been thought a small inclination of the road towards the center where three scuppers, so avoid flooding along the facades of the buildings, as far as possible will be made.

general supply network with 232 linear meters of pipe will also be renewed, 236 linear meters underground pipeline for the supply of 16 new lights type LED street lighting will be realized and 590 meters of pipeline will be placed for the burial of the low voltage lines and 205 linear meters for telephony.

In addition, the containers are soterrarán at the intersection of the street Marsilla with Santiago.

At the meeting, residents learned about the report from the technical service responsible for parks and gardens that reported the poor condition of the copies of casuarina equisetifolia there in the square, and the bad scars detailing the cup, the cup unbalanced, the unbalanced growth, exudates, excessive weight, cracks, vegetative amurallamiento, wounds and large cavities of the trunk and a cavity is introduced tronqué underground, with branches whose insertion into the trunk is very weak due to the plywood they were subjected in the past and have been sometimes breaking them.

In conclusion of the meeting, and after evaluating the structural mechanical problem, the loss of resistance to higher loads with respect to the throne, will be subject to greater mechanical stress, with a likelihood of failure of these specimens was subjected to a vote of neighboring the future of this woodland, deciding by majority replacement by at least four new trees conveniently develop in urban areas.

The mayor of Works said "thanks to the commitment of the regional president Pedro Antonio Sanchez and the Minister of Public Works and Infrastructures, Francisco Barnabas, continue to improve Lorca hand of their neighbors."

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información