Portal de Lorca

www.portaldelorca.com

Lorca - SpanishLorca - English
detail of Lorca

 

More than 4,000 residents will benefit from the new Collector General Sanitation Campillo (22/06/2009)

The hamlets of Campillo and Cazalla Lorca will benefit from the end of 2010, the new Collector General Sanitation, as reported by the City Council Water and Environment of the City of Lorca, Melchor Morales.

This infrastructure, the cost amounts to more than 4.5 million euros, is part of the recovery plan of the municipality of Lorca Disseminated, plan fully funded by the Directorate General of Water of the Ministry of Agriculture and Water of the Government of the Autonomous Community .

In particular, the work will involve the installation of 5 miles of pipe of 1,200 mm in diameter, including the Farm School and the Rambla de Viznaga therefore complement the work of the Collector to be made between the boardwalk and the Farm School Tiata.

As pointed out by Councilman Melchor Morales, this action will mean "a major modernization of remediation of Lorca, and benefiting over a thousand households in the XXI century, no sewage system, having to use septic tanks which will now be replaced" .

According to Morales, the new Collector General Sanitation Campillo provide two very important benefits, "on one side will prevent the infiltration of sewage into the ground while on the other hand, water is recycled for further treatment at Treatment Station Wastewater La Hoya, through which these flows can be reused for irrigation of vegetables. "

Councilman Water and Environment has indicated that, after completion of all works of Disseminated Sanitation Plan of the municipality of Lorca, which includes the Collector, "all wastewater from the municipality of Lorca will be treated, which is a very important news for the environment Lorca, as well as an improvement that was in the neglect of previous socialist governments. "

In this sense, Morales has stressed that "from the Government Team of the City of Lorca and the Autonomous Community of Murcia demonstrated, once again, our sensitivity and our commitment to the environment because, not surprisingly, the amount of all the works included in the Plan of Sanitation of the City of Lorca have cost 70 million euros, a very important figure for some key actions to our municipality. "

The works will be undertaken for 10 months, it is estimated that by the end of 2010 more than 4,000 residents Cazalla Campillo and will benefit from this collector.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información