Works in Old Harbor Crossing, which represent an investment of 103,200 euros, will be ready for next August (13/07/2009)

The works are being carried out by a Lorca, which employs 5 workers |

Councilman Works and Services of the Municipality of Lorca, Angel Mecca, reported that the work being undertaken for improving the street Old Harbor Crossing will be completed, if no unforeseen circumstances, over the next August .

Mecca has indicated that the work that has been agreed with the citizens living on this street, is included in the Municipal Investment Plan, PIMUN, and are financed by the FEIL.

The mayor said that "this street deserved an improvement of this magnitude that should be made in advance.

This is a neighborhood to demand that from the city council had the political intention to respond in the shortest time possible.

In fact it has been the mayor, Francisco Jodar, who has shown special interest since the first time for you to carry out this project.

The execution of these works, as happens in so many that we are doing in different streets of the village, is the pedestrian as the main character.

In this regard it is noteworthy that the pedestrians will have wider sidewalks and properly adjusted to the current accessibility standards. "

From the Department of Works has indicated that work on the Journey Old Port, one of the corners of the city's development, provide further correction sanitation collector.

Mecca Angel explained about "residents in the area sent us its concern at the fact that whenever rainfall were recorded more or less force the private parking garages and appeared even suffered flooding and sewage.

Because of these facts we set out to find out what the circumstances that motivated these episodes.

Finally found the cause was that when it came to installing the current sanitation collector was not taken into account the slope of the road, so is the infrastructure that kept evacuated.

This is a "surprise" more than we inherited from the way we do work that characterized previous municipal corporations. "

Mecca Angel noted that the works in Old Harbor Crossing, which began about 35 days, will be ready over the next August, if there is more news.

The works will greatly benefit the residents, since it also includes the change of pavements and road resurfacing.

The investment is to be made for the execution of this work is at € 103,200.

The project, in 5 people work is being carried out by a company Lorca.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información