The works of the new waste management glass of Barranco Hondo will culminate this month and will place Lorca as a national treatment and recovery model (11/07/2018)

Investments in these facilities will save 5.8 million euros annually.

The new glass is expected to have a useful life of around 40 years, 55% more efficient than the previous one, with an increase in capacity of 254%.

The Mayor of Lorca, Fulgencio Gil, along with the delegated councilor of Limusa, Juan Francisco Martínez, has supervised the notable advances and improvements with respect to the original project that have been registered throughout the execution of the works corresponding to the new glass for the treatment of urban waste.

It is a work of great importance and strategic nature, whose benefits will be reflected throughout the municipality.

The Mayor has indicated that the justification for undertaking this work arises from the need to increase the storage capacity of Urban Solid Waste (RSU) of the Barranco Hondo Management Center and proceed to the closure of the current container vessel.

The works are being executed based on legal criteria and current environmental standards.

The first mayor recalled that the new glass of the CGR will be 55% more efficient and cheaper than the previous one, multiply by 4 its useful life and places Lorca as a national model in waste treatment.

The investments in Barranco Hondo will allow Lorca to save annually 5,857,456.44 euros between travel costs and handling of urban waste.

Among all Lorca we are raising a new Lorca, which marks the challenge of looking to the future by executing the infrastructures that our social groups and their own reality showed.

In this way, it is so important in our city model to have more and better roads, water supply networks and renovated services, a modern Fair and Congress Center, as well as a recovered historical heritage, safety infrastructures, and streets and neighborhoods properly prepared and equipped, such as having facilities in which the waste we generate is treated in the most appropriate manner.

The total capacity of the facility is 2,826,000 m3.

The increase compared to the current glass, which has served 9 years and 7 months, is 254%.

The amount of the new glass is 2,253,711.14 euros, 55.46% cheaper than the previous one.

In fact, its efficiency also round this amount, exactly 55.58%, since the capacity of this cell 3 is estimated close to 2 million tons, compared to the current 562,000.

The entry into operation of this infrastructure is expected on January 8, 2019 and its duration is estimated in about 40 years, taking into account the data verified in the history of urban waste disposal in the last 18 years.

The landfill will be divided into three sub-cells, so that filling will be done in phases, working on a third of the surface.

In this way the production of leachates is minimized.

Thanks to this project is going to solve an environmental problem of treatment and recovery of waste generated in family and industrial areas, providing the municipality with an area of ​​two million square meters in which to store the waste generated by the population at all levels, in addition to ensuring the recovery of the valuable material for recycling, paper, cardboard, glass, organic matter, packaging, etc.

As general data of the work we must mention the following:

Bidding budget: € 6,685,641.13

Adjudication Budget: € 4,336,975.40

Start date of work: June 30, 2017

Execution term of the works: 12 months.

Justified delay in the execution period: 32 days due to force majeure (rains).

Percentage of work executed to date: 85.78%

Of the remaining 14.22%, 7.75% corresponds to work to be executed and 6.47% to the supply of a waste compactor machine.

Fulgencio Gil has explained that the following actions are included in this work:

Construction of the RSU vessel in Cell 3: Volume of ground movement under ground level: 1,443,800 m3, with three interior sub-cells, equipped with independent drainage and leachate extraction systems.

The cell has been overlapped with cell 1. Average capacity of the vessel between levels 1,550,000 m3.

The improvements implemented during the execution of the work have been:

Execution of intermediate security berm on the slope This for anchoring and access of maintenance personnel during operation.

Execution of a glass of storms and intermediate safety berms in the event of landslides in the excavation area.

Sealing and Closing of Cell 2: Sealing surface of the closed cell: 55,800 m2.

Sealing system by means of mineral impermeable barrier and artificial drainage system based on hidden geocomposite with discharge to perimeter ditches and cover layer of topsoil of 1 m.

Leachate extraction: 3 independent booths, one per subcell, equipped with independent extraction systems by means of hydraulic bottom pumps, with mechanical protection of the extraction columns by means of concrete pipes, controlled from the main house and equipped with a level probe for control of leached.

Accesses and gutters: Surface of new service roads: 9,050 m2, surface of accesses and current roads to resurface: 18,005 m2, length of the new concrete gutters for drainage: 2,540 m.

Improvements made during execution:

Improvement of the section of the main access road, with a category elevation up to a section T-00 for heavy traffic in anticipation of heavy traffic.

Paving access to the interior of the cell.

Paving the exit service path cell 3.

Execution of safety barrier for traffic on service road C-3.

Renovation of an additional 1,500 meters of perimeter fencing.

Environmental Integration and Visual Impact Improvement: Vegetable hydroseeding surface in cell 2: 55,000 m2, length of new cypresses hedges: 2,954 m (8,900 trees), automated irrigation in all vegetation sectors.

Improvements made during execution:

Additional clearing of fencing perimeters for defense against rabbit pests of 20,000 m2.

Stormwater Raft: expansion of the existing raft (300 m3) to 20,000 m3, for the storage and use of rainwater from ditches and its use for irrigation of vegetation.

Improvements made during execution:

Expansion of the storage capacity of the rainwater basin in 4,025 m3, having a total capacity of 24,025 m3.

Lighting: optimization and energy efficiency, by replacing the current lighting with another type of low consumption LEDs: 100 low consumption light points, construction of new underground pipes: 4,300 m.

Improvements made during execution:

Centralization of all systems in the new office building.

Update of the luminaires including point-to-point telemanagement system.

Office building: construction of a new office building of 250 m2 built for 6 work stations, access control and a training room for 26 people.

Improvements made during execution:

New electrical connection from the transformation center.

Centralization of all electrical systems and control from the building.

Exterior safety glass.

New supply installation.

New sanitation installation.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información