Students of the Mixed Employment and Training Program "CASCO HISTORICO II" make improvements in the vicinity of the Bakers' Poster (24/11/2019)

The Councilor for Local Development of the City of Lorca, Isabel Casalduero has explained that in recent weeks there have been actions in the vicinity of the Cartel, with the aim of improving this area of ​​the city.

The mayor of Local Development has detailed that masonry, electricity and painting have been carried out.

Specifically in terms of masonry, a team has been responsible for carrying out the removal and cleaning of existing weeds and weeds in this area.

Once the road was cleaned, small areas repaired in previous actions were detected as loose stones with different materials and different cavities where there was no material, so this paved road has been consolidated by cleaning and joining, to the once the areas where there was no material have been replaced, using the same procedure of placement and type of stone, achieving with this action a continuity and homogeneity of material throughout the road, eliminating the danger that existed for the pedestrian ".

On the electricity works, Casalduero, explained that "they have consisted of the removal of two obsolete street lamps that were on the facade of the building, and a new Led street lamp with the same type existing in the street has been placed in the building opposite For the ornamental lighting of the building, 5 LED spotlights have been placed.

Casalduero has pointed out that "it has also been acted on the walls and walls of the street Poster and its surroundings. Works that have consisted of the removal of graffiti, the removal of degraded paint that exists in the walls, the covering of fissures and damage , the product application to consolidate the areas in poor condition and subsequent application of two hands of white finished paint ".

The mayor of Development has specified that "this intervention has been carried out with the Mixed Employment and Training Program" CASCO HISTORICO II "managed by the Department of Local Development, in which six students and a masonry monitor: Pavements and masonry have participated of urbanization; nine students and a monitor, for the one of Painting: Auxiliary operations of continuous coatings in construction; and ten students and a monitor for the one of Electricity: Auxiliary operations of assembly of electrical installations.

The material execution budget has amounted to 2,800 euros and the execution period during which these works have been carried out has been three weeks.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información