The Councilor for Works and Local Development in the City of Lorca, Lali Ibarra, has reported that more than fifty Lorca companies are participating in the process of building the new Congress Center and Exhibition Center thanks to the collaboration of different administrations Is being developed in Santa Quiteria.
Lali Ibarra stressed that this is an emblematic and necessary project for our city and our region, thanks to which we will promote in a very prominent way the role of Lorca as a subregional capital and undisputed territorial head.
We are talking about a modern, functional and operative infrastructure that will respond to the needs expressed by the different socio-economic agents and the business community of Lorca.
The Center of Congresses and Fairgrounds of Lorca will constitute an economic and activity revulsive for the whole municipality.
It is an infrastructure widely demanded by Lorca, whose construction is progressing according to schedule.
It should be remembered that the implementation of the first phase has already been completed, leading to an investment of around 7 million euros.
This first impulse was possible to the relentless work of raising funds that has led to the conclusion of our Mayor, Francisco Jódar, which resulted in the obtaining of Feder funds to finance the action.
Ibarra López has indicated that currently is working on the materialization of the second phase of the Fair, which includes as a highlight the construction of the ship that will host the animal samples live, which will serve events of extraordinary relevance In the local calendar of fairs such as the National Week of Porcine Cattle (Sepor) and the Fair of the Horse (Fericab).
The execution of this second phase, which will also benefit all the neighbors of the surrounding streets thanks to the urban renovation of the streets Santa Quiteria, Horno and Alameda Virgen de las Huertas, is being carried out by a Temporary Union of Companies (UTE ) With Lorca participation, encouraging the increase of the business and labor activity of our city as a direct consequence of the
Economic and cultural revulsion widely demanded by Lorca society
Now phase 2 with UTE Lorca ship alive live
Work in 3 phases1 with ERDF funds
2ª now in work loan EIB urbanization streets nearby and important collector
No delays, progress as expected
Infrastructure that if it depended on the PSOE we would never have it, and there we have the committed commitment of ZP`
Tranquility.
Works out of political controversy, intense work of the Mayor without any kind of
18 million and a half
Sticks in the wheels, advancing perfectly to enjoy the lorquinos and welcomes many fairs motor of economic impulse and generation of employment and singerias.
7, 3.7 now, to complete 7 million
Source: Ayuntamiento de Lorca