This is the sector for the industrial estate 1.A.2.I Saprelorca.
The total surface area is over 254,000 meters squared.
It generates a green area of ​​25,000 m2, and other equipment of around 15,000 m2.
Councilman Urban Area of ​​the Municipality of Lorca, Francisco Garcia, has informed that the Local Government Board held on Friday April 1, adopted as final the draft of the so-called Private Sector 1.A.2.I Polygon Saprelorca the Diputación de Torrecilla, site of the multinational Noksel.
These development works are carried out in 2 phases for a maximum period of 12 months.
In the development works of the first phase will be provided with all necessary services and complete the commercial development Noksel, whose opening is imminent and that currently the Town Planning has already begun the process to grant Opening Licence.
The total cost of the development works amounting to a sum of € 3,783,903 to be disbursed by the entity Saprelorca.
The Town Planning has indicated that among the most significant of this sector we can highlight:
- Surface Sector254.632 m²
- 96,094 m² Plot Area Noksel
- Other Parcelas1.100 and 3,500 m²
- Area 8,835 m² General Systems
- Equipment 14,868 m²
- 25,270 m² Green Zone
It should be noted that the buildable under the PGMO is a total of 151,936 square feet of roof, which corresponds to the city of Lorca a total of 15,194 m² under the relinquishment of 10%.
Also, these infrastructure works will generate a total of 814 parking spaces, of which 28 will go to the disabled.
Francisco Garcia has declared that it is good news, a major investment for our town in addition to allowing the settlement of commercial Noksel, will offer a good number of plots to allow industries to continue settling in this Polygon Lorca, one of the pointers in our region.
Source: Ayuntamiento de Lorca