This is an area equivalent to 111 football fields reflecting the interest of the City for the development of industrial activity in the town
The Town Planning of the City of Lorca, José Joaquín Peñarrubia, has reported that the city council will approve this morning foreordination an industrial sector of Serrata.
Peñarrubia explained that this measure will order an overall surface of 500,000 m2, which corresponds to the space they occupy 111 fields, will be defined further green areas and road sector benchmark.
The main advantage of this approval is that it allows the licensing of industrial facilities without the need for the development of the partial plan.
This is a measure that will benefit all owners of this area, and whose processing has been agreed with them.
Manzanera Peñarrubia explained that it is the General Plan Amendment No. 62 nonstructural on basic foreordination Serrata developable land zoned 4-I.
This procedure has been reported favorably from the point of view of the Technical and Legal Service of the City Planning.
We propose a general system of open spaces located along the Rambla Salada bordered on the east by the sector with an area of ​​76,304 m2, which complies with the determinations of the information about the sector.
We propose a comb road system, consisting of a longitudinal road running through the area from north to south, bordering the general system of open spaces and a perpendicular to the main road connecting the existing road.
This amendment modifies only the sector level, which contains a basic foreordination, including general system of open spaces and main road.
This modification does not alter the other parameters included in the tab sector, collects only a transitional building that was not covered above.
This procedure is based on the industrial and commercial installations existing prior to the approval of the General Plan, which operate in the field of action, consistent with the overall use of the sector and to enable the proper growth market needs, as appropriate in the current times of economic and financial crisis, so they can carry out improvements, renovation and expansion of facilities to enable its adaptation to the current legislation, and since the general plan did not foresee in his a transitional moment that would maintain its activity, it is considered necessary to carry out the modification of Lorca PGMO to preorder the sector and allow such actions
It is proposed as a new tab in the sector as follows:
FINDINGS OF THE SECTOR
AREA SECTOR
470,881 m²
GENERAL SYSTEMS SURFACE
76,304 m² SG EL-4
SURFACE (Excluding SG)
394,577 m²
Uses detailed
Industrial (M-1: 27 125 m2)
Industrial (M-2: 88 436 m2)
Industrial (M-3: 40 468 m2)
Industrial (M-4: 57 747 m2)
Industrial (M-5: 37 901 m2)
Sc = 22,837 m² t
Sc = 74,458 m² t
Sc = 34,072 m² t
Sc = 48,620 m² t
Sc = 31,910 m² t
ACHIEVEMENT
0.45 m t / m s (Including General Systems) (1)
0.84193 m t / m s (Applicable to net plots)
CATEGORY
Industrial
(1) The use of reference applies to the total area of ​​the sector including general systems.
PROGRAMMING AND MANAGEMENT
PLANNING FIGURE
Partial Plan and Action Plan
PLANNING INITIATIVE
Public
SYSTEM PERFORMANCE
Cooperation
PROGRAMMING
2 ° quadrennium
BUILDING CONDITIONS
TYPOLOGY
Isolated Warehouse
CONDITIONS OF MANAGEMENT
The general system of open spaces will be located as graphic determinations attached, however it may consider another site similar proportions not admitting the disintegration of the surface of the SG, necessarily linked to a major road sector management of defining Partial Plan, where justified its greater suitability.
TRANSITIONAL
Foreordained sector establishes the following conditions for building up the drafting development planning:
Building conditions:
Type of building: Isolated.
Minimum Plot: 2.500 m². (*)
Minimum frontage: 20 m. (*)
Minimum setback: 3 m boundary. (*)
Buildable: 0.45 m² / m²
Maximum height: the need for industrial activity.
Number of plants: those required for industrial activity.
Basement: YES
CONDITIONS OF INFRASTRUCTURE SERVICES CONNECTIONS
WATER DISTRIBUTION
Artery connection D 300 planned to plant Purines
SANITATION
Connecting to collector and new WWTP Curtidos
ELECTRICITY
Serrata substation and high connection to 132kV LMAT hallway.