The Minister of Public Works and Planning, Antonio Sevilla, last night attended the reopening of the railway line linking Lorca Eagles with their service now reset normally.
Antonio Sevilla stressed the comprehensive performance of the works of repairing the damage of this line held in the past four months by the Railway Infrastructure Administrator (ADIF).
The works have been implemented both in infrastructure (embankments, trenches, bridges and drainage works) and the superstructure (via protection equipment level crossing) and its adequacy in anticipation of future risks from weather.
The most important activities have focused on a total of 16 kilometers of the stretch, Aguilas and Lorca involves an investment of seven million euros.
Source: CARM