The hostel Casa Grande de Coy will benefit from a comprehensive performance improvement achieved an investment of 50,000 euros (01/06/2015)

The improvement works in this manor house dating back to the eighteenth century, it is scheduled to last two months and will focus on repairs to roofs, façade and inside the building.

The Town Planning in the City of Lorca, Francisco Garcia, has reported that the city council will invest € 49,450.50 to proceed with the execution of the Municipal Rehabilitation Project property that houses the hostel Casa Grande de Coy, typical manor eighteenth century.

We are talking about a performance that has as main purpose to repair the damage caused by the earthquake in the building, briefly described below, without altering the building area of ​​the outer shell is produced, or any other urban feature of the property that is, they have no safety or affected stability.

Garcia explained that this is an isolated building, composed of several bodies, resolved with a support structure of load-bearing walls, with wrought wooden beams and joists with gypsum cankerworm.

The cladding system consists of masonry walls.

The roof of the building is tilted, made with wooden beams and joists as reeds and mud plaster inside plaster.

The cover is finished with Arabic tiles.

This building has all the necessary connections of facilities such as water, electricity, sewage, etc.

As a result of the earthquakes occurred in 2011, were detected, among others, the following flaws:

- Damage covered: partial detachment of the cover in the area of ​​the building called traditional wine cellar.

Landslides and specific deformations in the remaining cover.

- Damage to the facade: has several cracks that while not pose an imminent risk if ruin the aesthetics of the building and compromise the sealing of the same.

There are several natural stone plates placed in the base of the building that are detached.

- Damage inside: as a result of the deterioration suffered in the roof of the building and with the passage of time there have been numerous inputs of water into the building.

There are therefore many areas where it will have to chop the damaged and replaced by a coating and paint.

In some wet cores peeling occurred tiling and timely release of the plates making up the false ceiling.

The building has three floors.

The floor consists of exhibition area, facilities, workshops, toilets and 2 patios.

First floor bedroom, dining room, kitchen, recreation room and bathroom and second floor 5 bedrooms, two bathrooms and attic are located are located.

It should be noted that implementation of the plan of arrangement does not provide for the modification of surfaces constructed or carried out any change of use, which initially had maintained the building.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información