The Department of Employment and Work of the City of Lorca concludes remodeling three streets, finalizing the other eight have in hiring another six, although I expected put up for tender in the coming months other six with the goal of realizing the comprehensive improvement of This area of ​​the city.
Councilmember Employment, Construction and Local Development of the City of Lorca, Eulalia Ibarra has reported that, thanks to a grant received from the Department of Development of the Regional Government, the Consistory Lorca is running throughout this year and is in the process hiring the remodeling of 17 streets of San Pedro, representing a more than 1.7 million euros investment.
Ibarra was speaking at the opening of the street improvements Father Garcia Carlón Father and Father Morote, which represents an investment of 235,973.11 euros, and stressed that "especially the latter, parallel to the street Selgas, is a street widely used because it is located several courts. "
Specifically, these streets are being acted on 1,088 m2, where it demolished the existing pavement for later replacement by 964 m2 cobblestone black and red and 124 m2 of paving stone.
This investment has also included the replacement of the existing asbestos cement pipe from the mains supply by other casting of a meter in diameter, and the renewal of 190 meters corresponding to the sewer and storm pipes that will have PVC manholes and 6 are replaced.
They also scupper 21 meters to collect rain installed.
As for the lighting, there have been 260 meters underground piping for installation of street lights and 17 lights are replaced with new ones led type.
It has also enabled a network of 270 meters underground to channel low voltage lines and over 115 meters to do the same with telecommunications networks.
The works have been executed in these ways, as in the rest of the districts, aimed at encouraging Lorca to return to live in these streets so close to the city center to ensure better quality of life for people inhabit them, because they are modernizing not only in surface but the best infrastructure of services that exist today are installed, giving a major qualitative leap in terms of comfort, lighting, ...
Eulalia Ibarra explained that "are being finalized the works of the streets Sol, Torrevieja, Moon and Tudela in the same neighborhood, which represent an investment of 235,974.48 euros, while it is running improving Camino Viejo de San Pedro, Córdoba Ramirez Medrano and investing 239,669.36 euros ".
In addition, currently in the process of hiring remodeling Alfonsina streets 366,294.5 euros, Albaricos and Charity by 238,253.75 euros and Guiraos, Crossing The Guiraos and ensures 398,780.51 euros.
Also put up for tender is expected in the coming months remodeling the streets Mayor, All, Child, shovels, Cabezo and crossing all financed by the Autonomous Community.
Source: Ayuntamiento de Lorca