The Department of Works explained that the works will be completed on the section linking the square of Spain with the Mother of God School and at Mata, Soler and cruise Soler, while work will continue on from the educational center the escalericas.
The Mayor of Lorca, Francisco Jodar has reported that "remodeling Calle Cava and adjacent will be executed in more than 60% for the start of the school year, having concentrated most of the action in the summer months to interfere as little as possible in the classroom and the inputs and outputs of the Mother of God Mercy College and Conservatory of Music ".
In fact, as has proven the mayor during his visit to the works by the Councilman Hall Works of Lorca, Eulalia Ibarra, the development of this investment is running in installments so that "those days will be concluded Part of the road linking the square of Spain with the school and on the street Mata, Soler and Soler crossing, connecting with Santiago Street and Plaza del Iberreño ".
"From that moment, the works on the route linking the school with escalericas so that access and evacuation in case of a supposed emergency start is guaranteed," said the mayor.
The remodeling of Calle Cava and adjacent Mata, Soler and Soler Crossing, involving an investment of 434,737.5 euros from the Ministry of Public Works of the Autonomous Community.
Jodar explained that these four streets of our historic quarter and add to the comprehensive reform of the city that began in the neighborhood of Vine to increase the quality of life of Lorca, but also aims to connect the enhanced neighborhood San Juan and the medieval walls to the central square of Spain.
The mayor stressed that "the project includes the necessary demolition of 1,550 m2 of pavement to replace it with pavers best qualities and calcite marble and black granite after replacing the network of water supply and sanitation, the creation of a network storm, replacing 22 lamps by others of the same type style classic but led, will facilitate energy saving, complying with the municipal commitment to reduce CO2 emissions into the atmosphere and reducing the cost of electricity consumption. "
Francisco Jodar has indicated that "once this work will have been buried 650 meters of cabling street lighting and piped Iberdrola appropriate place for the burial of low-voltage lines."
The works, which have a lead time of about six months, also channeled a new telecommunications networks.
In addition to acting that runs from the bow of the Collegiate of San Patricio to the confluence with the street Marsilla, staircase linking this street with the bridge of the Pool, will be paved with marble peldañeada be demolished, installing a new rail stainless steel.
"Ultimately, it's about putting the last of underground services this street and public lighting, also placing six spotlights LED indirect lighting Arch Street Cava" said the mayor.