The regional government next week will auction the works of Lorca neighborhoods of Alameda, Apolonia and Los Angeles for 10.5 million euros (25/09/2015)

The Minister of Public Works and Infrastructures, Francisco Barnabas, today announced the upcoming financing of new actions of urban renewal in the Alameda de Cervantes and the barrios of Los Angeles and Apollonia, in order to "maintain the investment in the Autonomous Region for the recovery of the city of Lorca. "

Barnabas stressed that these actions will have a budget of 10.5 million euros, provided by the regional government office contracted by the Community to the European Investment Bank (EIB) loan.

These actions will soon begin the process of contracting with project bidding and construction, which, according to Barnabas, "notes that the commitment of the regional government is maintained at the same level as the first day and will continue until construct the new Lorca , to return to the city the splendor that was before the tragic earthquake. "

These two projects are part of a second agreement between the Ministry and the Municipality of Lorca, which provides for the execution of other works aimed at urban renewal, "necessary to promote the recovery of economic and social activity of the municipality."

Barnabas made the announcement during an inspection visit to the assembly site of the new tower high voltage electrical service will Lorca La Viña, prior to the removal of existing and belonging to the former electrical substation tower Rambla the ladies.

Moving the pylon

The Minister stressed that the transfer of the pylon, located at Weavers, across the road from Granada and the Boulevard of the Ladies and the underground line 66 kilowatts "is one of the commitments by the Ministry in urban renewal district of La Vina, satisfying the demands of the residents of Lorca. "

The work, which began in the middle of this September, "making good progress in the redesign and installation of the new tower and the underground passages, which will soon make the final dismantling of the existing tower and finish Weavers street access road to Granada, "said Barnabas.

After an initial phase in which they have implemented the lines of the new underground power line of 66 kW, it has concrete caisson of the four supports of the new tower is assembled in situ around the frame of the metal tower .

Then we will proceed to installing the new air support on its final base, the discharge of the electrical grid and the new connection, which will be simultaneously and publicly communicated to the neighbors for general knowledge and avoid possible incidents.

The performance will end with the withdrawal of existing support and develop the new end of the road connecting the road Weavers Granada.

The transfer of the pylon is part of the urban renewal district of La Viña, which has had a budget of 5.8 million euros and in which the most notable works are the repair and improvement of urban infrastructure electricity, sanitation and water supply, as well as the pedestrian road to promote accessibility and connection between neighborhoods.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información