Councilman Planning, Francisco Garcia presented the agreements adopted by the Town Planning Board held last March 18.
These include the Final Approval of the Action Plan and the requirement for a single unit Reparcelación Performance Study Detail 2 of PGMO located in Lorca Granada Road.
This program was initially approved in December 2007.
This is a project presented at the initiative of the owners of land where, in addition to its legal obligations, undertake to perform additional development works, consisting of the adequacy of the road edge and the performance of green spaces and were assigned in advance, with an area of 4,900 m2, which must be added the 7,617 that are within the performance.
García ha destacado que “el proyecto se desarrolla en una parcela de 28.340 m2 de los que 7.617 están destinados a espacios libres de parques y jardines y 10.082 estarán destinados a viales y aparcamientos.
La edificabilidad total de ámbito es de 44.500 m2 y como consecuencia de la cesión al ayuntamiento, éste obtendrá una edificabilidad de 4.700 m2â€.
Â
The budget for implementing the development works amounting to € 1,823,201.
Final approval of Amendment No. 1 Spot's Catalogue PEPRI Sector 2 of the Historic-Artistic Site, Villa No. 16, Block 4.
Similarly, in the Council Planning Department on Wednesday agreed to Final Approval of the Amendment Spot # 1's Catalogue PEPRI Sector 2 of the Campus Historic preservation, farm 16, block 4, located on Calle Santo Domingo Juan de Toledo de Lorca.
This is possibly a building constructed in the late eighteenth and early nineteenth centuries and although it was originally the home, was used at a time as the temporary seat of White Pass.
Probably the most distinctive element is outside the turret that remains on the curved tile roof and in their interior, highlighted the great staircase and the existence of paintings in some rooms.
The mayor noted that "the current situation of the building is severely deteriorated, presented fissures, cracks and landslides in different walls, collapse of part of the floor and roof, damage to the tower, on the stairs, subsidence in pavements, etc., the building does present a degree of deterioration and substantial alteration. "
While the building's architectural value is not remarkable, except in some of its unique elements, "does have an environmental value for their situation, which requires the conservation of its exterior to preserve conjunction with the existing adjacent buildings."
The Heritage Service of the Department of Fine Arts and Cultural Heritage, issued a favorable report on the performance on January 18, 2008, which authorized the consolidation and rehabilitation of the facade interior drain current for reconstruction while preserving those elements, their size should be kept, for which the report concludes that after the works must be rebuilt the access, the ladder and the tower, to be removed during construction and then recover and rehabilitate both paintings existing on the first floor of the building, such as carpentry and locksmithing.
This report is confirmed by the January 27, clarifying that the bill does not represent the change in the degree of protection but a realization of the determinations of the tab of the property in a manner designed to address specific aspects that facilitate the performance of rehabilitation and facilitate the adjustment to the adjoining buildings.
"Depending on the degree of protection afforded by this property PEPRI," he pointed García, "it was possible the reconstruction and preservation of the facade and interior of the building emptied, so due to its current state, could result declaration of bankruptcy, which would result if the permanent loss not only of the property, but those parts which led to its protection.
Hence the interest shown by culture in their recovery, interest is shared by the City, so the formula has been sought to ensure that those elements of the building to be preserved and retained effectively recover and recover. "
For this purpose promoted the amendment of PEPRI tab to allow the proceedings involving the reconstruction and preservation of the facades and the interior of the building drain to the terms of the main staircase and the tower will be rebuilt according to its original facade will be rebuilt in the overhangs of the balconies and reset the fence that once were withdrawn by the City Council about the danger posed by their detachment, and should keep the paintings in the room on the first floor, and proceeded to withdrawal before the start of work and placing them in the same room while respecting their original characteristics, all according to the report of Department of Fine Arts and Cultural Assets.
Installation and licensing activity.
Moreover, the Board of Management Installation License granted to manufacturing activity in the industrial awnings La Hoya.
Similarly, definitive license has been granted for a store opening in wholesale of beverages in the industrial area of La Hoya.
Withdrawals.
The Board of Management has also agreed to the suspension of activity due to numerous neighborhood complaints received and local police reports, two bars, one in Loch Street and another on Avenida Juan Carlos I.
Certifications works.
Finally, the Management Board also authorized the payment of certificates of commercial works as follows:
"SAPRELORCA" the amount of € 113,628 for certifications No. 1 and No. 2 by the works of "bike lanes in the old road to Granada."
Source: Ayuntamiento de Lorca